Copper Anode Casting Line Commissioning Checklist

A stage-by-stage walkthrough of cold trials, first heat and performance testing so the anode weight accuracy of ±1% is proven before handover.

An anode casting line is accepted on statistics, not on a demonstration. A machine can index correctly and pour clean plates all afternoon, then miss the weight criterion of ±1% on ≥98% of plates once mould temperature drifts across a full shift. The sequence below keeps mechanical and metallurgical evidence separate: pre-commissioning checks prove the installation, cold trials prove the motion and interlocks, the first heat proves the pouring recipe, and the performance test proves the statistics before handover.

Pre-Commissioning Checks

Start with the mechanical installation, not the control system. Confirm turntable level against the foundation drawing, check that the ladle clears the mould train through a full revolution, and rotate the disc by hand before any servo is energised. Verify the central dual-servo disc drive is coupled and aligned, that the mould temperature control circuit holds pressure, and that the barium sulphate dry-powder coating station is mounted at the working height above the mould face. Any of these found late will be blamed on the casting recipe during the first heat.

Utilities come next. Confirm the PLC and host computer exchange data, that recipes download without timeout, and that every interlock on the ladle, turntable and mould cooling loop reports the correct state. Weighing instrumentation needs a current calibration record before the first plate is poured, because the whole acceptance argument rests on it. Also walk the emergency stops and the reject path with the line empty, so that a later fault is a process problem rather than a wiring surprise.

  • Foundation bolts torqued and turntable level verified against the general arrangement drawing
  • Mould cooling and temperature control circuits pressure tested and vented
  • Servo axes jogged in manual with travel limits and interlocks proven
  • PLC to host computer handshake and recipe download confirmed
  • Anode weighing system calibrated with a traceable record before first pour
  • Cold Trials

    Cold trials run the entire cycle at production speed with an empty ladle and cold moulds. The purpose is repeatability: the turntable should stop at the same position every revolution, the ladle tilt profile should complete within the cycle time, and the automatic coating cycle should cover the cracked areas of each mould without manual touching. Record the parameters that will be compared later during the first heat, because a cold trial that is not logged proves nothing at handover.

  • Index one full revolution and log stop position repeatability at each station
  • Dry-cycle the ladle tilt and pouring profile at the production cycle time
  • Run the barium sulphate coating cycle on cold moulds and inspect coverage
  • Trigger a simulated weight fault and confirm the reject path and alarm
  • First Heat

    The first heat is a tuning exercise, not a production run. Pour a short series of anodes, weigh every plate individually, and adjust the quantitative casting cut-off before widening the sample. On a machine rated for 160–400 kg anodes, the cut-off that suits one plate weight will not suit another, so fix the target weight first and leave it alone. Watch the coating cycle time, nominally 3–5 s, against the actual cycle: if coating eats into the cycle, back-fin and sticking defects will appear on the anode surface later.

    Mould temperature is the second variable. The automatic mould temperature control is there to hold the face condition stable over a shift, so set it early rather than chasing defects plate by plate. If the moulds are new, expect the first anodes to sit slightly outside the weight band while the mould faces settle; note them, do not compensate with the cut-off. Log every deviation with its timestamp so the performance test can distinguish a settling-in effect from a genuine control problem.

    Performance Test

    The performance test converts the tuning work into evidence. Run at the rated capacity of the installed model and record every plate, not a sample, across a full shift. Weight accuracy is judged as ±1% on ≥98% of plates, so the statistic must be computed over the whole shift population; a good hour is not a result. Capacity targets differ by machine configuration, so fix the target before the test begins and do not renegotiate it afterwards.

    Test parameterAcceptance basisRecord to keep
    Anode weight range160–400 kg as orderedIndividual plate weights
    Weight accuracy±1% on ≥98% of platesShift statistic per size
    Casting capacityRated plates/h of the modelCounter log full shift
    Coating cycle time3–5 s per mouldPLC timestamps
    Mould temperatureStable across the shiftTrend chart per mould
    Surface defectsNo back-fin or sticking trendVisual inspection sheet

    The capacity figures give a quick sanity check on the configuration under test: 120 plates/h for the single-turntable single-ladle machine, 200 plates/h for the single-turntable double-ladle, 260 plates/h for the double-turntable double-ladle and 400 plates/h for the double-turntable four-ladle arrangement. ZXSZ builds all four on the same PLC + host computer platform, so the same record format and statistics can be used across models. A shortfall of a few plates per hour at a given rating is usually a cycle-time issue rather than a casting problem.

    Handover Documents

    Handover is a document set, not a signature. The operator needs the parameters that actually passed the test, and the maintenance team needs the settings that were changed during tuning, including cut-off, coating dwell and mould temperature setpoint. A handover file that lists only the nominal specification will not help when the mould set is replaced, the coating thickness changes and the anode weight drifts away from the target band.

  • Signed cold trial and first heat records with every setpoint used
  • Weight statistics per shift compared with the ±1% on ≥98% criterion
  • Mould temperature and coating cycle logs exported from the PLC
  • Spare parts list covering ladle, mould and coating consumables
  • Maintenance schedule for the central dual-servo disc drive and turntable
  • Design the acceptance protocol around the statistic, not the plate. Write the test population, the shift length and the calculation method into the purchase specification before the machine arrives, so that ±1% on ≥98% of plates is a measurable clause rather than a discussion at handover. Keep the cold trial and first heat logs in the same file as the performance test, and require the PLC trend exports to be delivered with the handover documents; those exports are the only objective record of how the turntable, ladle and mould temperature behaved while the weight criterion was being met.